A single machine work center has five jobs assigned to it. Theyare labeled in the order of their arrival in the shop as jobs AB C D and E. The work center may work on only one job at a timeand must complete any job it starts before starting another job.Job A has a processing time of 6 days and is due to the customer in9 days. Job B has a processing time of 2 days and is due in 16days. Job C has a processing time of 4 days and is due in 10 days.Job D has a processing time of 3 days and is due in 7 days. Job Ehas a processing time of 5 days and is due in 12 days. Using theshortest processing (operating)) time priority rule what will bethe average tardiness of these orders?2.62.03.0